In Srinivasa Reddy Velagala v. Sravanthi Infratech, 2026 INSC 835, the Supreme Court set aside insolvency proceedings arising from a Rs 827 crore EPC contract for a 225 MW gas-based power plant in East Godavari. The Court held that the EPC contract subsisted and was not frustrated, and that unpaid milestone payments are operational debt, while suspension, idling and demobilisation charges are unliquidated damages that are not operational debt until adjudicated. Although the corporate debtor’s seven-year silence meant there was no pre-existing dispute, the claim was barred by limitation since it crystallised in early 2012 and legal notices from the creditor cannot extend limitation.

Key Takeaways

  • Milestone payments under an EPC contract are operational debt under Section 5(21) IBC.
  • Suspension, idling and demobilisation charges are damages and are not operational debt until assessed by a competent forum.
  • Frustration under Section 56 of the Contract Act does not apply to self-induced frustration from a party’s own breach.
  • Consistent and total silence over years in response to legal notices can be strong evidence of no pre-existing dispute.
  • Legal notices sent by the creditor do not extend limitation; Section 18 needs acknowledgement by the debtor.
  • IBC is not meant to give a new lease of life to time-barred debts (Babulal Vardharji Gurjar).

Case Details at a Glance

Case titleSrinivasa Reddy Velagala v. Sravanthi Infratech Pvt. Ltd.
Citation2026 INSC 835 (Reportable)
Case numberCivil Appeal No. 876 of 2021
BenchJustice J.B. Pardiwala and Justice Manoj Misra
Authored byJustice J.B. Pardiwala
Date of judgment12 August 2026
Impugned orderNCLAT, New Delhi judgment dated 01.02.2021 in Company Appeal (AT) (Insolvency) No. 188 of 2020
Law involvedSections 5(21) and 9, Insolvency and Bankruptcy Code, 2016; Section 18, Limitation Act, 1963; Section 56, Indian Contract Act, 1872
Counsel who arguedMr. Shyam Divan, Senior Advocate, for the appellant; Mr. Nitin Bhardwaj, Advocate, for the respondent Sravanthi Infratech Pvt. Ltd.
ResultAppeal allowed; NCLAT and NCLT orders set aside; liberty to respondent to pursue arbitration under the EPC contract

Facts of the Case

Sravanthi Infratech was awarded the EPC contract worth Rs 827 crore on 24 December 2010 and an agreement was signed on 9 February 2011. Of Rs 165.4 crore due on the first three milestones, only Rs 50.15 crore was paid. The contractor suspended work by notice of 30 July 2011.

The developer acknowledged the work and liability by letters of 5 January 2012 and 3 February 2012. The contractor sent legal notices in 2014 and 2015, which went unanswered, and later filed a Section 9 application. NCLT Amravati admitted it, and NCLAT affirmed.

Timeline of Proceedings

  • 24.12.2010Letter of Award for Rs 827 crore.
  • 09.02.2011EPC agreement.
  • 30.07.2011Notice of suspension by contractor.
  • 05.01.2012 and 03.02.2012Acknowledgements of liability.
  • 2014 to 2015Legal notices by contractor, unanswered.
  • 01.02.2021NCLAT upholds admission.
  • 12.08.2026Supreme Court sets aside admission.

Issues Before the Supreme Court

  1. Was the EPC contract frustrated by efflux of time?
  2. Were the amounts claimed operational debt?
  3. Was there a pre-existing dispute?
  4. Was the Section 9 application time-barred?

Arguments and Counsel

Appellant (Mr. Shyam Divan, Senior Advocate)

The claim was time-barred since dues were quantified and acknowledged by 2012; acknowledgement only renews the debt for three years; legal notices raised disputes; the contractor should have gone to arbitration.

Respondent (Mr. Nitin Bhardwaj)

Suspension did not terminate the contract, which still subsisted; non-payment of advances and milestone dues was admitted; the demand notice was valid.

Supreme Court’s Ruling

1. Contract subsisted

Neither party terminated under Clause 14, time was not of the essence, and frustration cannot be self-induced (Boothalinga).

2. Operational debt in part

Milestone payments are operational debt; suspension, idling and demobilisation charges are damages that must be crystallised by adjudication first.

3. No pre-existing dispute

No litigation or arbitration was pending, and total silence for seven years indicated no dispute under Mobilox.

4. Time-barred

Claims crystallised on the 2012 acknowledgements; the creditor’s own notices cannot extend limitation, so default occurred over three years before filing.

Result

The admission of the Section 9 application was set aside as the claim was time-barred. The operational creditor is at liberty to pursue its claims before the dispute resolution forum under the EPC contract. A copy goes to the NCLAT for circulation to all NCLTs.

Analysis and Practical Points

The judgment is useful for construction and infrastructure contractors: they must pursue claims within limitation, and damages-type heads cannot found an insolvency petition. For corporate debtors, it confirms that silence may defeat a pre-existing dispute plea, but limitation remains a strong defence.

  • Operational creditors: File within three years of default or the last debtor acknowledgement; do not rely on your own legal notices.
  • EPC contractors: Separate milestone dues from damages claims, which belong in arbitration.
  • Corporate debtors: Respond to demand notices; silence may defeat a later pre-existing dispute plea.

Frequently Asked Questions

What did the Supreme Court decide in 2026 INSC 835?

It set aside the CIRP admission against the power project developer because the Section 9 application was time-barred.

Are idling and demobilisation charges operational debt?

No. They are damages and cannot be operational debt until adjudicated.

Do legal notices extend limitation under IBC?

No. Section 18 of the Limitation Act requires acknowledgement by the debtor.