Section 20, 20A, 20B, 20C of Specific Relief Act 1963

 

SUBSTITUTED PERFORMANCE OF CONTRACT ETC

Section 20. Substituted performance of contract

(1) Without prejudice to the generality of the provisions contained in the Indian Contract Act, 1872 (9 of 1872), and, except as otherwise agreed upon by the parties, where the contract is broken due to non-performance of promise by any party, the party who suffers by such breach shall have the option of substituted performance through a third party or by his own agency, and, recover the expenses and other costs actually incurred, spent or suffered by him, from the party committing such breach.

(2) No substituted performance of contract under sub-section (1) shall be undertaken unless the party who suffers such breach has given a notice in writing, of not less than thirty days, to the party in breach calling upon him to perform the contract within such time as specified in the notice, and on his refusal or failure to do so, he may get the same performed by a third party or by his own agency:

Provided that the party who suffers such breach shall not be entitled to recover the expenses and costs under sub-section (1) unless he has got the contract performed through a third party or by his own agency.

(3) Where the party suffering breach of contract has got the contract performed through a third party or by his own agency after giving notice under sub-section (1), he shall not be entitled to claim relief of specific performance against the party in breach. (4) Nothing in this section shall prevent the party who has suffered breach of contract from claiming compensation from the party in breach.

 

Section 20A. Special provisions for contract relating to infrastructure project

(1) No injunction shall be granted by a court in a suit under this Act involving a contract relating to an infrastructure project specified in the Schedule, where granting injunction would cause impediment or delay in the progress or completion of such infrastructure project.

Explanation.-For the purposes of this section, section 20B and clause (ha) of section 41, the expression "infrastructure project" means the category of projects and infrastructure Sub-Sectors specified in the Schedule.

(2) The Central Government may, depending upon the requirement for development of infrastructure projects, and if it considers necessary or expedient to do so, by notification in the Official Gazette, amend the Schedule relating to any Category of projects or Infrastructure Sub-Sectors.

(3) Every notification issued under this Act by the Central Government shall be laid, as soon as may be after it is issued, before each House of Parliament, while it is in session, for a total period of thirty days which may be comprised in one session or in two or more successive sessions, and if, before the expiry of the session immediately following the session or the successive sessions aforesaid, both Houses agree in making any modification in the notification or both Houses agree that the notification should not be made, the notification shall thereafter have effect only in such modified form or be of no effect, as the case may be; so, however, that any such modification or annulment shall be without prejudice to the validity of anything previously done under that notification.

 

Section 20B. Special Courts

The State Government, in consultation with the Chief Justice of the High Court, shall designate, by notification published in the Official Gazette, one or more Civil Courts as Special Courts, within the local limits of the area to exercise jurisdiction and to try a suit under this Act in respect of contracts relating to infrastructure projects.

 

Section 20C. Expeditious disposal of suits

Notwithstanding anything contained in the Code of Civil Procedure, 1908 (5 of 1908), a suit filed under the provisions of this Act shall be disposed of by the court within a period of twelve months from the date of service of summons to the defendant:

Provided that the said period may be extended for a further period not exceeding six months in aggregate after recording reasons in writing for such extension by the court.