Section 67 - Effect of neglect of promisee to afford promiser reasonable facilities for performance : Indian Contract Act 1872

What is the Effect of neglect of promisee to afford promiser reasonable facilities for performance? Section 67 of Indian Contract Act 1872


 

Section 67 of Indian Contract Act 1872 : "Effect of neglect of promisee to afford promiser reasonable facilities for performance"

67. If any promisee neglects or refuses to afford the promiser reasonable facilities for the performance of his promise, the promiser is excused by such neglect or refusal as to any non-performance caused thereby.

Illustration
A contracts with B to repair B's house.

B neglects or refuses to point out to A the places in which his house requires repair.

A is excused for the non-performance of the contract if it is caused by such neglect or refusal.